Industry has expressed apprehension on several points in the Land Acquisition Bill, which might be taken for discussion in Parliament on Thursday.
The apprehensions cover several aspects, from the definition of ‘project affected’ to the requirement to seek consent of at least 80 per cent of such families in acquiring land.
Industry bodies told Business Standard the new processes the Bill would add to the procedures would considerably increase the time taken to acquire land. The Federation of Indian Chambers of Commerce and Industry (FICCI) says at least five years would be required now to get land to start a project. The Confederation of Indian Industry (CII) says the Bill would raise the cost of acquisition five-fold. Both have opposed the provision to apply the provisions with retrospective effect.
The high floor for consent of those affected is one of the points opposed by both FICCI and CII. The latest amendments, tabled in Parliament last year, stipulate that acquition for private companies as defined under ‘public purpose’ requires prior consent of at least 80 per cent of the affected families is mandatory. For public-private partnership projects, where ownership of the land continues with the government, prior consent of at least 70 per cent of the affected families is mandatory.
CII says the provision of consent should be reduced to 60 per cent of land owners, uniformly and equally applicable to all cases, irrespective of its end-use. FICCI says the definition of project affected families is too wide and it would be practically impossible to identify the genuine ones and attain their consent.
Compensation package
Cost of compensation is another complaint. If the Bill’s provisions go through, the cost of land acquisitiony is likely to increase by 3-3.5 times, severely affecting the viability of industrial projects across the board and eroding the competitiveness of the manufacturing sector, says business. CII says no solatium should be imposed over and above the multiplier formula. If at all solatium is to be retained, it should be reduced to 30 per cent and the multiplier be reduced to 1.5 times instead of twice.
Another grouse is that the Bill would raise relief and rehabilitation (R&R) costs three-fold, as the proposed package treats/compensates different categories of affected families at par. Also, the most recent amendments provide that in cases where land is acquired for urbanisation, 20 per cent of the developed portion is to be reserved and made available to project affected families, in proportion to the area of their land acquired and at a price equal to the cost of acquisition and the cost of development.
CII says: “Instead of using the broad term of ‘affected families’, the category of families needs to be clearly defined and according to their losses, a suitable compensation package should be laid down.”
In the proposed amendments, the limits for direct purchase may be notified by the appropriate government, considering the relevant state-specific factors and circumstances.
Further, it stipulates filing an application with the district collector, notifying him of intent, purpose and particulars of the land to be purchased.
CII says: “As sellers would have received the premium on land value, provisions of R&R should not be applicable to land owners in such cases. However, suitable R&R entitlements could be laid down for affected families who lose their livelihood as a result of such acquisition.
Further, the provision that provides for filing an application with the district collector, notifying him of such land purchase can make the entire project unviable, as:
(1) In the time period taken for such approval, land prices will shoot up
(2) Whenever a private person/company commences purchasing land, prices tend to increase substantially
(3) Even if agreements are entered into for purchase of land, such agreements shall not carry any validity.
Hence, it says, this provision should be removed from the Bill.
Irrigated multicrop land
The limits on acquisition of multi-cropped land may be notified by the appropriate government, considering the relevant state-specific factors and circumstances, says the Bill.
CII says: “Restrictions on acquisition of multi-cropped land should not be applicable in the case of mineral extraction projects, as minerals occur naturally and, hence, their locations cannot be chosen.”
Return of unutilised land
In the proposed amendments, when any land acquired under the new Act remains unutilised for five years from the date of taking over the possession, it same shall be returned to the original owner or owners or their legal heirs to the land bank of the appropriate government by reversion, in a manner determined by the appropriate government.
CII says: “Industry must submit a land-use plan and the provision of return of unutilised land should be aligned to it, to be decided by a committee under the chairmanship of the chief secretary of the state concerned, on a case to case basis.
Retrospective applicability
The Bill stipulates that in cases where an award under Section 11 (of the old law) has not been made, the process would lapse upon enactment of the new Bill and the process of acquisition would have to start afresh.
CII and FICCI both say the retrospective clause will only add to uncertainty. The Bill should have only prospective application. Also, in cases where the notification under section 11 has already been issued and the process of award has commenced, these should be continued as stipuleted in the old law, to avoid lengthy delays in land acquisition and consequent cost over-run.
Urgency clause
The Bill stipulates that in cases of urgency, whenever the appropriate government so directs, “the collector…. shall take possession of any land needed for a public purpose and such land shall vest absolutely in the government, free from all encumbrances”.
CII says: “This clause should also be applicable in the case where after the award has been made, people do not come forward to accept it. Adverse possession should be taken over and encumbrance-free land be handed over to the requiring body.”
Public hearings
Social Impact Analysis (SIA) proceedings need to be carried out in consultation with the panchayat, municipality or municipal corporation concerned, at village or ward level.
CII says: “Public Hearings for SIA and environment vlearances should be combined. It would help reduce the overall project implementation schedule. Further, such SIA study be carried out as a parallel activity to acquisition and not as a condition precedent. Otherwise, the whole process will take a very long time and the purpose of acquisition shall be defeated, as project costs will shoot up.”
Possession of acquired land
The Bill stipulates that the distrcit collector should take possession of acquired land only after the entire compensation and R&R entitlements are disbursed.
CII says as in the existing Land Acquisition Act of 1894, the collector should be empowered to take possession after 80 per cent of the affected families have accepted and received the compensation.
Lease option
FICCI says: “Leasing has its own set of disadvantages. Leases have inherent uncertainty regarding renewals, particularly when the period is short. A lease may restrict flexibility over development and operations, adding further to uncertainties. Also, leased lands will impact mergers and acquisitions, as there are obvious limitations to the automatic transmission of leases in rearrangements. All this needs to be evaluated before making it a part of the Bill.”
Slowing of industry
One major concern of FICCI is that the time required to acquire any land will now increase significantly. The time required will be five to six years on an average, since a number of steps have been added to the whole process. There is now the IA, the public hearing for this, the evaluation of the SIA report by an expert group, getting 80 per cent consent and validating it in the SIA report, public hearing for R&R, etc.
R&R for private deals
For large projects in manufacturing in the private sector, the Bill says the government will not have any role in acquisition. Industry’s complaint: “So, for large steel and cement plants, land will have to be acquired by industry, which might face problems due to ‘last mile acquisition’. However, the R&R provisions will still apply to private transactions above the specified threshold land area. Application of R&R to private transactions on a willing buyer-willing seller basis defies economic logic.”